Item 17 - Award of Bid Old Poway Park Train Barn Pit Expansion Project
AGENIY-REPORT SUMMARY
TO: Honorable Mayor and Members of the City Council
Honorable Chairman and Members of the
Redevelopment Agency
FROM: James L. Bowersox, City Manager/ExecUti~rector
INITIATED BY: Robert L. Thomas, Director of Community Services ~
James D. Bentz, Community Services Manager ~~
DATE: November 12, 1996
SUBJECf: Award of Bid for the Old Poway Park Train Barn Pit Expansion Project ((#5602)
ABSTRACf
This proposal would award the Train Barn Pit Expansion construction contract to Single Eagle,
Inc., in the amount of $26,000. The contract time for the project is sixty working days.
ENVIRONMENTAL REVIEW
This item is not subject to CEQA review.
FISCAL IMPACf
There are sufficient funds in the Old Poway Park construction fund for this project.
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
Additional notification sent to John Ohler, Poway-Midland Railroad Volunteers.
RECOMMENDATION
It is recommended that the City Council/Redevelopment Agency award the Old Poway Park Train
Barn Pit Expansion Project construction contract to Single Eagle, Inc., in the amount of $26,000
and authorize staff to proceed with the project.
ACfION
1 of 3
IWV 1 2 1996 n c:t~ 17
~ AGENDA REPORT
CITY OF POW A Y
This report is included on the Consent Calendar. There will be no separate discussion of the report prior to approval by the
City Council unless members of the Council. staff or public request it to be removed from the Consent Calendar and
discussed separately_ If you wish to have this report pulled for discussion, please fill out a slip indicating the report number
and give it to the City Clerk prior to the beginning of the City Council meeting.
TO:
Honorable Mayor and Members of the City Council
Honorable Chairman and Members of the Rede~~ment Agency
James L. Bowersox, City Manager/Executive Di~
Robert L. Thomas, Director of Community Services ~
James D. Bentz, Community Services Manager~~
FROM:
INITIAlED BY:
DAlE:
November 12, 1996
SUBJECf:
Award of Bid for the Old Poway Train Barn Pit Expansion Project
(#5602)
BACKGROUND
This project was bid previously on May 9, 1996. Only one bid in the amount of
$31,567.92 was received. The bid was rejected and staff was authorized to redesign the
project in order to attract more competitive bids.
On October 17, 1996, bids were opened for the Old Poway Park Train Barn Pit
Expansion Project. The engineer's estimate was $20,000. The contract time for this
project is sixty days.
FINDINGS
The following two bids were received:
Company
Bid
Single Eagle, Inc.
San Diego, CA
$26,000
Fordyce Construction
Santee, CA
$34,000
ACTION:
))
2 of 3
re'! 1 ~ E95
[~-"D
. :.:. ~~J
", -
- (
Agenda Report
November 12, 1996
Page 2
ENVIRONMENTAL REVIEW
This item is not subject to CEQA review.
FISCAL IMPACf
There are sufficient funds in the Old Poway Park construction fund for this project.
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
Additional notification sent to John Ohler, Poway-Midland Railroad Volunteers.
RECOMMENDATION
It is recommended that the City Council/Redevelopment Agency award the Old Poway
Park Train Barn Pit Expansion Project construction contract to Single Eagle, Inc., in the
amount of $26,000 and authorize staff to proceed with the project.