Item 1.14 - Ext. of FY 18-19 St. Main. Proj. Contract for FY 19-20 Zone 3 St. Maint. Proj.; Bid 18-022City of Poway COUNCIL AGENDA REPORT DATE: June 18, 2019 TO: Honorable Mayor and Members of the City Council FROM: Robert Manis, Director of Development Services CONTACT: Jeff Beers, Special Projects Engineer (858) 668-4624 or jbeersApoway.orq SUBJECT: Summary: APPROVED ❑ APPROVED AS AMENDED ❑ (SEE MINUTES) DENIED ❑ REMOVED ❑ CONTINUED RESOLUTION NO. Extension of the Fiscal Year 2018-2019 Street Maintenance Project Contract for the Fiscal Year 2019-2020 Zone 3 Street Maintenance Project; Bid No. 18-022, American Asphalt South, Inc. The Fiscal Year 2019-2020 Street Maintenance Project consists of placement of type II emulsion aggregate slurry and polymer modified chip seal along with raising water, sewer and monument lids flush to grade. This work will take place within Street Maintenance Zone 3 which generally are the streets south of Twin Peaks Road, east of and including Pomerado Road, north of Poway Road and west of Tarascan and Silverset Roads. Recommended Action: It is recommended that the City Council extend the Fiscal Year 2018-2019 Street Maintenance Contract for the Fiscal Year 2019-2020 Zone 3 Street Maintenance Project in the amount of $1,075,753.47. Discussion: On June 19, 2018 the Fiscal Year 2018-2019 Street Maintenance Project was awarded to American Asphalt South, Inc. This contract includes a provision that allows for the contract to be extended. This is the first of two allowable extensions. American Asphalt South, Inc. successfully executed and completed the Fiscal Year 2018-2019 Street Maintenance Project and submitted new unit prices, as required by the contract documents, that have been reviewed and accepted by staff. The cost of most of the work within the project remained the same as last year. Some unit costs increased within expected escalation rates. All provisions of the Fiscal Year 2018-2019 Street Maintenance Contract will remain except for the description of the Fiscal Year 2019-2020 Street Maintenance Project Zone 3 scope of work. Environmental Review: The proposed asphalt/concrete pavement rehabilitation of existing City streets with the Fiscal Year 2019-2020 Street Maintenance Project is Categorically Exempt from the California Environmental Quality Act (CEQA) as a Class 1 Categorical Exemption, pursuant to Section 15301(c) of the CEQA Guidelines, in that the project involves maintenance of existing streets with no expansion of use. 1 of 2 June 18, 2019, Item #1.14 Fiscal Impact: The Proposed Budget for Fiscal Year 2019-20, which will be considered by Council on June 18, 2019, includes $458,100.00 in account 0411040-43203, $791,900.00 in account 0411040-43205, and $8,000.00 in account 415010-43040. This is to extend the Fiscal Year 2018-2019 Street Maintenance Project contract for the Fiscal Year 2019-2020 Zone 3 Street Maintenance Project in the amount of $1,075,753.47, upon adoption of the proposed budget. Public Notification: None. Attachments: None. Reviewed/Approved By: Reviewed By: Approved By: Wendy Kaserman Alan Fenstermacher Assistant City Manager City Attorney 2 of 2 Chris Hine City Manager June 18, 2019, Item #1.14