Item 17 - Visual Slideshow provided by Staff at MeetingESPOLA ROAD SAFETY IMPROVEMENTS –PHASE 2CONSTRUCTION CONTRACT AWARD
Project ScheduleUtility Undergrounding March 2019 – August 2021Phase 2 Improvements Design August 2019 –May 2021Construction Bid May 2021 –July 2021Construction Start September 2021Anticipated Construction Completion March 2022
Utility Undergrounding Districts20A 20B
Project DetailsBefore
Project DetailsCurrent Proposed Improvements
Project Details
•Contractor: Tri‐Group Construction and Development•Local San Diego firm•Previous Poway experience includes Valle Verde Park Playground Renovations, Annual CMP Repair/Replace, and Poway Road Turn Pocket Extension projects•Total Construction Contract ‐$1,899,805•Project Duration –Six months•Neighborhood meeting will be held before construction startsProject Details
Discussion