Item 20 - Award of Bid for Lake Poway Playground Project
AGENDA REPORT SUMMARY '""""'
TO: Honorable Mayor and Members of the City Council
_FROM: James L. Bowersox, City Man~
INITIATED BY: John D. Fitch, Assistant City Manage~t-
James R. Williams, Director of Public rvices ~
Daniel W. Cannon, Parks and Landscape Manage.
DATE: January 3, 1995
SUBJECT: Award of Bid for the Lake Poway Playground Project
ABSTRACT
Bids were opened at 3:00 p.m. on November 30, 1994 for the reconstruction of the Lake
poway Playground adjacent to the Pavilion.
Three bids were received with Court Concepts of San Diego being the low bidder. It is
recommended that the City Council award the Lake poway Playground Project to Court
Concepts of San Diego, California in the amount of $50,049.14.
ENVIRONMENTAL REVIEW
This project has been determined to be categorically exempt from CEQA environmental
- review requirements.
FISCAL IMPACT
The bid amount is over the amount budgeted for this phase and it is recommended that
$15,000 be reprogrammed from the poway Bridge Project. Both projects are funded with
Community Block Grant funds. The poway Bridge Project has been completed and has
sufficient funds remaining to cover the additional cost of the playground project.
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
Court Concepts, 12260 Katydid Circle, San Diego, California 92129.
Tarzian Landscape Construction, 2736 Madison Street, Carlsbad, California 92008.
Edward A. Zasueta Contracting Co., P.o. Box 866, Spring Valley, California 91976-0866.
RECOMMENDA TION
It is recommended that the City Council award the Lake poway Playground Project to
Court Concepts of San Diego, California in the amount of $50,049.14.
ACTION
-
1 of 3 JAN 3 1995 17c;vl 20
~AGENDA REPORT
CITY OF POWAY
This repM is included on the Consent Calendar. There will be no separate discussion of the report prior to approval by the
City Council unless members of the Council. staff or public request it to be removed from the Consent Calendar and
discussed separately. If you wish to have this report pulled for discussion. please fill out a slip indicating the report number
and give it to the City Clerk prior to the beginning of the City Council meeting.
TO: Honorable Mayor and Members ~ city Council
FROM: James L. Bowersox, City Mana
INITIATED BY: John D. Fitch, Assistant City Manage~ ~
James R. Williams, Director of Public ervices
Daniel W. Cannon, Parks and Landscape Manager~
DATE: January 3, 1995
SUBJECT: Award of Bid for the Lake poway Playground Project
BACKGROUND
Staff has completed a design for the renovation of the Lake poway Playground,
adjacent to the Pavilion. The project was designed in two phases in conjunction
with separate funding sources. Phase 1, this project, includes retaining walls,
sidewalks, disabled accessible playground equipment, benches and grading. All.
of these facilities are designed and will be constructed as accessible to the
disabled community. This portion of the project is funded by a Community Block
Grant. Phase 2 includes the remaining playground equipment and is funded through
the Park Land Dedication fees.
FINDINGS
Three contractors attended the pre-bid meeting on November 15, 1994 and inspected
the playground plans and site. Three contractors submitted the following bids
on November 30, 1994:
Court Concepts $50,049.14
San Diego, California 92129
Tarzian Landscape Construction $49,890.00
Carlsbad, California 92008
Edward A. Zasueta Contracting Company $54,317.00
Spring Valley, California 91976
Court Concepts was the lowest qualified bidder. Staff received positive
comments regarding their services from references they contacted. Tarzian
Landscape Construction was the lowest bidder but they did not have the specified
contractors license.
ACTION:
2 of 3 JAN 3 1995 lïi:¡W 20
-- -,
- Agenda Report - Award of Bid for the Lake poway Playground Project
January 3, 1995
Page 2
ENVIRONMENTAL REVIEW
This project has been determined to be categorically exempt from CEQA
environmental review requirements.
FISCAL IMPACT
The bid amount is over the amount budgeted for this phase and it is recommended
that $15,000 be reprogrammed from the poway Bridge Project. Both projects are
funded with Community Block Grant funds. The poway Bridge Project has been
completed and has sufficient funds remaining to cover the additional cost of the
playground project.
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
Court Concepts, 12260 Katydid Circle, San Diego, California 92129
Tarzian Landscape Construction, 2736 Madison Street, Carlsbad, California 92008
Edward A. Zasueta Contracting Co., P.O. Box 866, Spring Valley, California 91976
RECOMMENDATION
It is recommended that the City Council award the Lake poway Playground Project
to Court Concepts of San Diego, California in the amount of $50,049.14.
JLB:JRW:DWC:mmc
JAN 3 1995 r;i:M 20