Item 10 - Award of Bid The Auxiliary Generator Building AGENDA REPORT SUMMARY
TO: Honorable Mayor and Members of the City Council f/~~
Honorable Chairman and Members of the
~ Redevelopment Agency
._~
FROM: James L. Bowersox, City Manage~
Executive Director
INITIATEDBY:Markd°hnD'iiiililAi!iiiiii~ii!~i~ii!i!~ger~rS]~Kipp S.R. e vice~7/~
DATE: March 7, 1995
SUBJECT: Award of Bid for The Auxiliary Generator Building (#5529)
ABSTRACT:
This proposal would award the Auxiliary Generator Building contract to CDM
(Construction Development Management) in the amount of $87,777.00. The contract time
for the project is 30 working days.
FISCAL IMPACT
There are sufficient funds to complete the project.
ENVIRONMENTAL REVIEW
This project is categorically exempt under Section 15301(f) of the CEQA.
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
None.
RECQMMENDATION
It is recommended that the City Council award the Auxiliary Generator Building contract
to CDM (Construction Development Management) in the amount of $87,777.00.
ACTION
~IAR 71995 ITEM- 10
lof3
-- AGENDA REPOR-
CITY OF POWAY
This report is included on the Consent Calendar. There will be no separate discussion of the report pdot to approvaJ by the
City Council unless members of the Council, staff or public request it to be removed from the Consent Calendar and
discussed separately. If you wish to have this report pulled for discussion, please ~11 out a slip indica~ng the report number
and give it to the City CIe~k pdor to the beginning of the City Council meeting.
TO: Honorable Mayor and Members of the City Council
Honorable Chairman and Members of the Redevelopment Agency
FROM: James L. Bowersox, City Manager/Executive Director
INITIAlleD BY: John D. Fitch, Assistant City Manager~ ,j
Mark S. Weston, Director of Engineerin~Service~'
Kipp R. Hefner, Associate Civil Engineer g~ /'
DA~: March 7, 1995
SUBJECT: Award of Bid for The Auxiliary Generator Building (#5529)
On February 9, 1995 bids were opened for the Auxiliary Generator Building
project. The Engineer's Estimate was $140,000 to $160,000. The contract time
for this project is 30 working days.
FINDINGS
The following eight (8) bids were received:
1. CDM (Construction Dev. $ 87,777.00
Management)
2. G.F. Bledsoe Construction $ 88,307.00
3. Jim Swartzwelder Const. $101,218.00
4. Castello, Inc. $103,000.00
5. HAR Construction $104,535.00
6. Khavari Construction, Inc. $104,800.00
7. Famania Construction Co. $117,634.00
8. Cunningham Construction Co. $118,795.00
ACTION:
2of3
I~AR 71995 ITEM 10
Agenda Report - Award of Bid for the Auxiliary Generator Building
March 7, 1995
Page 2
ENVIRONMENTAL REVIEW
This project is categorically exempt under Section 15301(f) of the CEQA.
FISCAL IMPACT
There are sufficient funds appropriated for the completion of the project.
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
None.
RECOMMENDATION
It is recommended that the City Council:
1. Award the Auxiliary Generator Building contract to CDM (Construction
Development Management) in the amount of $87,777.00.
]~AR ? 1995 ITEM 10