Item 11.3 - Acceptance of Construction or Poway Royal Mobile Estates Electrical System Rehabilitation TO: Honorable Mayor and Members of the City Council ~
Honorable Chairman and Members of the
-- Redevelopment Agency
FROM: James L. Bowersox, City Manager/Execu.~
Director
INITIATED BY: John O. Fitch, Assistant City Manage~ ~
Mark S. Weston, Director of Engineerin~ Service~~"~''
J. Bradley Kutzner, Senior Civil Engineer~
DATE: May g, 1995
SUBJECT: Acceptance of Construction of Poway Royal Mobile Estates Electrical
System Rehabilitation (5905)
ABSTRACT
Upon final inspection, staff finds the project to be in accordance with the standards
and specifications of the contract. It is recon~ended that the Redevelopment
Agency/City Council approve acceptance of this project°
ENVIRONMENTAL REVIEW
An environmental review was previously conducted which determined the project was
_ exempt. No additional environmental review is necessary.
FISCAL IMPACT
The project was completed within the budgeted amount. No additional funds are needed.
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
Mel Smith Electric, Inc.
RECOMMENDATION
It is recommended that the Redevelopment Agency/City Council:
1. Formally accept the improvements.
2. Authorize the City Clerk to file and re~ord a Notice of Completion.
3. Authorize release of the retention in the amount of $86,407.20.
ACTION
NAY9 1995 ITEM 11.3
'AGENDA REPORT
CITY OF POWAY
This repor~ is included on the Consent Calendar. There will be no separate discussion of the report pdor to approval by the
City Council unless members of the Council, staff or public request it to be removed from the Consent Calendar and
discussed separa e y f you wish to have this report pulled for discussion, please flu out a slip indicating the report number
and give it to the City Clerk prior to the beginning of the City Cound] meeting.
TO: Honorable Mayor and Members of the City Council
Honorable Chairman and Members of the Redevelopment Agency
.
FROM: James L. Bowersox, C~ty Manager/Executive Dir~
~
INITIATED BY: John D. Fitch, Assistant City Manager~ ~z~)
Mark S. Weston, D~rector of En~ineer!n~Services~
J. Bradley Kutzner, Senior Ciwl Eng~neerc~
DATE: May g, 1995
SUBJECT: Acceptance of Construction of Poway Royal Mobile Estates
Electrical System Rehabilitation (5905)
BACKGROUND
On December 15, 1991, the Redevelopment Agency awarded a contract to Mel Smith
Electric, Inc. for construction of the Poway Royal Mobile Estates Electrical
Rehabilitation. The amount of the contract was $1,504,825.
FINDINGS
Due to six change orders and changes in the final quantities, the amount of
the contract was increased by $223,318.97, for a total contract amount of
$1,728,143.97.
ENVIRONMENTAL REVIEW
An environmental review was previously conducted which determined the project
was exempt. No additional environmental review is necessary.
FISCAL IMPACT
The project was completed within the budgeted amount. No additional funds are
needed.
ACTION:
See Summary Sheet
2 OF 3 MAY 9 1995 ITEM 11,'3
-- Age~da Report - Acceptance of Powey Royal HobiLe Estates ELectricaL SVstem
Hay 9, 1995
Page 2
ADDITXONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
$mtth Electric, Inc.
recommended that the Redevelopment Agency/City Council:
1. Formally accept the improvements.
2. Authorize the C~ty Clerk to file and record a Not~ce of
Completion.
3. Authorize release of the retention in the amount of $86,407.20.
OLB:ODF:HSW:OBK:mh
3 OF 3