Item 16 - Award of Bid for Construction of Del Poniente Sewer Line
AGENDA REPORT SUMMARY ,-
TO: Honorable Mayor and Members of the City Council
_ FROM: James L. Bowersox, City Man~
^
INITIATED BY: John D, Fitch, Assistant City Manage~':t ~
Mark S, Weston, Director of Engineering Services
Javid Siminou, Senior Civil Engineer W
DATE: August 22,1995
SUBJECT: Award of Bid for the Construction of Del Poniente Sewer Line -
Phase I (#1803)
ABSTRACT
This proposal would award the construction of Del Poniente Sewer contract to Interwest
Pacific, Ltd, in the amount of $246,390.00. The contract time for the project is 60
working days,
ENVIRONMENTAL REVIEW
On June 6, 1995, the City Council issued a Mitigated Negative Declaration for this
proj ect. Approved mitigation measures being completed at this time include permit
applications for biological and cultural resources. The necessary permits are being
processed with consultant assistance so as to meet the construction schedule for the
- project, which is anticipated to start on September 1, 1995,
FISCAL IMPACT
There are sufficient funds to complete the project,
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
None,
RECOMMENDATION
It is recommended that the City Council award the Del Poniente Sewer contract to
Interwest Pacific, Ltd, in the amount of $246,390,00,
ACTION
-
AUG 2 2 1995 ITEM 16 .
! of 3
- AGENDA REPORT
CITY OF POW A Y
This report is included on the Consent Calendar. There will be no separate discussion of the report prior to ,approval by the
City Council unless members of the CounciL staff or public request it to be removed from the Consent Calendar and
discussed separately. If you wish to have this report pulled for discussion. please fill out a slip indicating the report number
and give it to the City Clerk prior to the beginning of the City Council meeting.
TO: ",o",b1. ',y" ,.d '"'b""~" City C,".,t1
FROM: James L, Bowersox, City Man
INITIATED BY: John D, Fitch, Assistant City Manager'\l't ~
Mark S, Weston, Director of Engineeri~ Services
Javid Siminou, Senior Civil Engineer
DATE: August 22, 1995
SUBJECT: Award of Bid for the Construction of Del Poniente Sewer Line
Phase I (#1803)
BACKGROUND:
On July 6, 1995 bids were opened for the Del Poniente Sewer Line Phase I
project, The Engineer's Estimate for the base bid was $205,000 to $235,000,
The contract time for this project is 60 working days,
FINDINGS:
The following eight (8) bids were received:
Base Bid Additive Alt, Total
1. Interwest Pacific Ltd, $238,890,00 $ 7,500,00 $246,390,00
2, L,R, Hubbard Const, $233,112,00 $20,000.00 $253,112,00
3, Western Pacific Const. $225,005,00 $50,000,00 $275,005,00
4, C,E, Wilson Corporation $283,928,40 $32,500,00 $315,928,40
5, Nashco, Inc, $290,679.54 $37,870.00 $328,549.54
6, Drainage Const. Co" Inc. $300,032,42 $30,000,00 $330,032,42
7. Don Hubbard Contracting $448,850,00 $22,000,00 $470,850.00
8, Civil Constructors Corp, Invalid Bid
FISCAL IMPACT:
There are sufficient funds appropriated for the completion of the project,
ENVIRONMENTAL IMPACT:
On June 6, 1995, the City Council issued a Mitigated Negative Declaration for
this project. Approved mitigation measures being completed at this time
ACTION:
AUG 2 2 1995 ITEM p,
. .
- -
Award of Bid for the Construction of Del Poniente Sewer Line Phase I (#1803)
August 22, 1995
Page 2
,-
include permit applications for biological and cultural resources. The
necessary permits are being processed with consultant assistance so as to meet
the construction schedule for the project, which is anticipated to start on
September 1, 1995,
PUBLIC NOTIFICATION & CORRESPONDENCE:
None,
RECOMMENDATION
It is recommended that the City Council award the Del Poniente Sewer Line
Phase I contract to Interwest Pacific Ltd, in the amount of $246,390,00,
JLB:JDF:MSW:JS:bw
-
AUG 2 2 1995 ITEM 16