Item 19 - Award of Bid for 95-96 Citywide Striping
AGENDA~EPORT SUMMARY
TO: Honorable Mayor and Members of the City Council
...ROM: James l. Bowersox, City Man~
INITIATED BY: John D. Fitch, Assistant City Manager~~1r ~
Mark S. Weston, Director of Engineering Service
Kipp R. Hefner, Associate Civil Engineer lCir
DATE: October 31, 1995
SUBJECT: Award of Bid for 95-96 Citywide Striping (#407-4330)
ABSTRACT:
This proposal would award the 95-96 Citywide Striping (#407-4330) to Traffic
Operations, Inc. in the amount of $41,969.17. The contract time for the project is 30
working days.
FISCAL IMPACT
There are sufficient funds to complete the project.
ENVIRONMENTAL REVIEW
This project is exempt under Section 15301 of the CEQA.
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
None.
RECOMMENDATION
It is recommended that the City Council award the 95-96 Citywide Striping (#407-4330)
contract to Traffic Operations, Inc. in the amount of $41,969.17.
ACTION
-
OCT 31 1995 ITEM 19 ,
1 of 3
----_.
AGENDA REPORT -
CITY OF POW A Y
This report is included on the Consent Calendar. There will be no separate discussion of the report prior to approval by the
City Council unless members of the Council, staff or public request it to be removed fr?": ~e ~onsent Calendar and
discussed separately. If you wish to have this report pulled for discussion, please fill out a slip !Octleating the report number
and give it to the City Clerk prior to the beginning of the City Council meeting.
TO: Honorable Mayor and Members of the City Council
FROM: James l. Bowersox, City Man~
INITIATED BY: John D. Fitch, Assistant City Manager~l~ ~
Mark S. Weston, Director of Engineering s~vice~~
Kipp R. Hefner, Associate Civil Engineer ~ .
DATE: October 31, 1995
SUBJECT: Award of Bid for the 95-96 Citywide Striping (#407-4330)
BACKGROUND
On October 18, 1995 bids were opened for the 95-96 Citywide Striping project.
The Engineer's Estimate was $60,000.00 to $70,000.00. The contract time for
this project is 30 working days.
FINDINGS
The following three (3) bids were received:
1. Traffic Operations, Inc. $41,969.17
2. Orange County Striping
Services, Inc. $48,442.88
3. ASAP Services, Inc. $49,845.05
ENVIRONMENTAL REVIEW
This project is categorically exempt under Section 15301 of the CEQA.
FISCAL IMPACT
There are sufficient funds appropriated for the completion of the project.
ACTION:
2 of 3 CT 3 1 1995
.-
-- Agenda Report - Award of Bid for the 95-96 Citywide Striping (#407-4330)
October 31,1995
Page 2
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
None.
RECOMMENDATION
It is recommended that the City Council award the 95-96 Citywide Striping
contract to Traffic Operations, Inc. in the amount of $41,969.17.
-
JDF\MSW\KRH:mhl
e:\city\agenda\strp1031.cip
-
OCT 3 1 1995 ITEM 19 .