Item 20 - Rejection of Bid for Del Poniente Sew Line
~ r-~ 1tY-'023-7s-
RhVISED
-. AGENDA REPORT SUMMARY
TO: Honorable Mayor and Members of the City Council
FROM: James L. Bowersox, City Mana~
INITIATED BY: John D. Fitch, Assistant City ManagerC\~ ~
Mark S. Weston, Director of Engineerin~serVice~'
Javid Siminou, Senior Civil Engineer
DATE: October 31, 1995
SUBJECT: Rejection of Bid for the Construction of Del Poniente Sewer Line
Phase I (#1803)
ABSTRACT
This proposal would reject the bids for construction of Del Poniente Sewer line.
ENVIRONMENTAL REVIEW
On June 6, 1995, the City Council issued a Mitigated Negative Declaration for this
-I'lroject. The mitigation measures, which have been under review for several months,
.nclude permit applications for biological and cultural resources. Due to delays in
issuing the permit, it is not likely that this project would be completed according to
the anticipated schedule.
FISCAL IMPACT
None.
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
None.
RECOMMENDATION
It is recommended that the City Council reject all bids for the Del Poniente Sewer
line.
ACTION
- OCT 311995 ITEM iO
AGENDA REPORT -
CITY OF POWAY
This report is included on the Consent Calendar. There wUl be no separate discussion of the report prior to approval by the
City Council unless members of the Council, stzIff or public ~equ~ It to be removed "?": ~e ~onsent Cl!llendar and
discussed separ8tely. If you wish to have this report pulled for discussion, please fill out e slip IndlC8ting the report number
and give it to the City Clerk prior to the beginning of the City Council meeting.
REVISED
TO: Honorable Mayor and Members~e City Council
FROM: James L. Bowersox, City Man
INITIATED BY: John D. Fitch, Assistant City Manage~1t ~J
Mark S. Weston, Director of Engineering Service~
Javid Siminou, Senior Civil Engineer ~
DATE: October 31, 1995
SUBJECT: Rejection of Bid for the Construction of Del Poniente Sewer
Line Phase I {#18031
BACKGROUND:
On July 6, 1995 bids were opened for the Del Poniente Sewer Line Phase I
project. The Engineer's Estimate for the base bid was $205,000 to $235,000.
The contract time for this project is 60 working days.
FINDINGS:
The following eight (8) bids were received:
Base Bid Additive Alt. .I2W
1. Interwest Pacific Ltd. $238,890.00 $ 7,500.00 $246,390.00
2. L.R. Hubbard Const. $233,112.00 $20,000.00 $253,112.00
3. Western Pacific Const. $225,005.00 $50,000.00 $275,005.00
4. C.E. Wilson Corporation $283,928.40 $32,500.00 $315,928.40
5. Nashco, Inc. $290,679.54 $37,870.00 $328,549.54
6. Drainage Const. Co., Inc. $300,032.42 $30,000.00 $330,032.42
7. Don Hubbard Contracting $448,850.00 $22,000.00 $470,850.00
8. Civil Constructors Corp. Inval id Bid
FISCAL IMPACT:
None.
ACTION:
2 of 3
.
Award of Bid for the Construction of Del Poniente Sewer line Phase I (#1803)
October 17, 1995
- Page 2
ENVIRONMENTAL IMPACT:
On June 6, 1995, the City Council issued a Mitigated Negative Declaration for
this project. The mitigation measures, which have been under review for
several months, include permit applications for biological and cultural
resources. Due to delays in issuing the permit, it is not likely that this
project would be completed according to the anticipated schedule.
PUBLIC NOTIFICATION I CORRESPONDENCE:
None.
RECOMMENDATION
It is recommended that the City Council reject the bids for construction of
Del Poniente Sewer line, and direct staff to readvertise the project for bids
once the environmental permits are issued.