Item 20 - Award of Bid Transit Stop Turnout & Shelter on Midland Rd.
- IJ~'-'~ //-c?,;}- 9:J-
AGENDA F ~T SUMMARY
TO: Honorable Mayor and Members of the City Council
- James L Bowersox, City Man~
'ROM:
INITIATED BY: John D, Fitch, Assistant City ManagefAl-r
Robert L Thomas, Director of Commu ty Service
Patrick R. Foley, Principal Management Analyst
DATE: November 28, 1995
SUBJECT: Award of Bid for Transit Stop Turnout and Shelter on Midland Road (1644)
ABSTRACT
This proposal would award the contract for the transit stop turnout and shelter on
Midland Road to Fox Construction in the amount of $64,912, The contract time for the
project is 60 working days,
ENVIRONMENTAL REVIEW
This proposed project is categorically exempt from CEQA under Class 3 new facilities.
'ISCAl IMPACT
There are sufficient funds budgeted in the bus shelter CIP account (1644) to construct
this project,
ADDITIONAL PUBLIC NOTIFICATION AND,CORRESPONDENCE
,
Additional notification sent to Fo~ Construction,
RECOMMENDATION
It is recommended that the City Council award the contract for the construction of the
Transit Stop Turnout and Shelter on Midland Road to Fox Construction in the amount of
$64,912, and direct that the work not start until after January 1, 1996.
ACTION
-
1 of 3 NOV 2 8 1995 ITEM 20 . ,
--
.!! AGENDA REPORT
CITY OF POW A Y
This report is induded on the Consent Calendar. There will be no separate discussion of the report prior to approval by the
City Council unless members of the Council, staff or public request it to be removed from the Consent Calendar and
discussed separately. If you wish to have this report pulled for discussion, please fill out a slip indicating the report number
and give it to the City Clerk prior to the beginning of the City Council meeting.
TO: Honorable Mayor and Members of the City Council
FROM: James L. Bowersox, City Man~
INITIATED BY: John D. Fitch, Assistant City Manager~~
Robert L, Thomas, Director of Community Service
Patrick R, Foley, Principal Management Analyst
DATE: November 28, 1995
SUBJECT: Award of Bid for Transit Stop Turnout and Shelter on Midland
Road (1644)
BACKGROUND
On November 15, 1995, bids were opened for the transit stop turnout and
shelter on Midland Road. The Engineer's Estimate was $55,000 to $65,000, The
contract time for this project is 60 working days.
FINDINGS
Two bids were received. They were:
Company Bid
Star Paving Corp. $71,582
San Diego, CA
Fox Construction $64,912
San Diego, CA
Since this project is located on Midland Road between Poway Road and Hilleary
Place, staff is recommending that the work not start until after January 1,
1996.
ENVIRONMENTAL REVIEW
This proposed project is categorically exempt from CEQA under Class 3 new
facil ities.
ACTION:
2 of 3 )
NaV 28 1995 ITEM 20
-
Agenda Report
Midland Road Transit Turnout
November 28, 1995
-- Page 2
FISCAL IMPACT
There are sufficient funds budgeted in the bus shelter CIP account (1644) to
construct this project.
ADDITIONAL PUBLIC NOTIFICATION AND CORRESPONDENCE
Additional notification sent to Fox Construction,
RECOMMENDATION
It is recommended that the City Council award the contract for the
construction of the Transit Stop Turnout and Shelter on Midland Road to Fox
Construction in the amount of $64,912, and direct that the work not start
until after January 1, 1996.